Testing of Systems including the Domestic Terminal at Argyle International Airport (AIA) will be conducted tomorrow February 7, 2017.

This is among several activities that have been taking place at the project site prior to the opening of the airport next week.

Tomorrow’s activity is scheduled to begin at nine in the morning.

Full operation of the Argyle International Airport will commence on February 14, 2017 at 6:45am with the departure of Liat flight 560.

Ferrying of LIAT Aircraft from E.T. Joshua Airport to AIA will be done on the evening of February 13.

The Argyle International Airport was constructed at a cost of over 700-million EC dollars.